Assessing the Post-Earthquake Temporary Accommodation Risks in Iran Using Fuzzy Delphi Method

All published articles of this journal are available on ScienceDirect.

RESEARCH ARTICLE

Assessing the Post-Earthquake Temporary Accommodation Risks in Iran Using Fuzzy Delphi Method

The Open Construction & Building Technology Journal 19 May 2021 RESEARCH ARTICLE DOI: 10.2174/1874836802115010093

Abstract

Background:

The process of temporary accommodation after an earthquake is one of the most important issues in crisis management.

Objective:

This research study attempts to identify and prioritize the key risks inherent with the post-earthquake temporary accommodation process in Sanandaj, Iran using the Fuzzy Delphi method.

Methods:

To achieve this goal, first, we examined the previous research on the issue of temporary accommodation after earthquakes and other disasters worldwide in order to determine the current important challenges. Then, the opinions of crisis management experts in 11 areas and 94 questions in the form of Fuzzy Delphi survey questionnaire with Five-point Likert measurement scale were used to rank these challenges. The Delphi panel participants, who responded to the Fuzzy Delphi questionnaire, consisted of 18 experts related to crisis management in executive organizations of Kurdistan province.

Result:

After performing the steps of the fuzzy Delphi method, a basket of important risks in the temporary accommodation process were identified qualitatively and quantitatively, and were prioritized in order of relevance and significance. The results showed that climatic challenges have the highest potential of post-earthquake temporary accommodation risk in the region among of the 11 major risk areas under examination.

Conclusion:

The study’s findings and recommendations can serve as a policy instrument and consultative toolkit for relevant stakeholders.

Keywords: Accommodation, Risk assessment, Crisis management, Fuzzy Delphi Method, Lawshe method, SPSS software.

1. INTRODUCTION

During the last decades, with the rapid development of infrastructure and urbanization worldwide, the role of crisis management and risk management in preventing irreversible losses in populated areas has become vital. A crisis, by a simple definition, is an unexpected event that threatens different levels of society, including human life, environment, and economy. Highly populated cities with dense infrastructure are the most vulnerable areas to such threats, which can be caused by natural disasters such as earthquakes, storms, and tsunamis [1]. The methods and techniques for dealing with such threats have been evolving in proportion to the severity and complexity of threats. Risk management is a powerful tool for minimizing and controlling the impact of unfortunate events to guarantee sustainable development [2]. Typically, crisis management consists of the identification, prioritization, and mitigation of potential risks. In this context, the risks with the greater impact and probability of occurrence are dealt with first, and this process continues for the less severe risks in descending order.

Every year, many buildings suffered significant damage due to natural disasters. In extreme cases, the buildings become inhabitable and unusable, which imposes a large economic burden on the government for managing the people who have lost their homes [3]. In such circumstances, governments use a housing restructuring policy, which consists of temporary and permanent accommodations. The former facilitates a fast recovery after a disaster, whereas the latter provides a safe place for victims to maintain their normal lives [4].

The preparation of families for the destructive consequences of an earthquake is profoundly influenced by their mindset. According to past research, people’s experiences from previous earthquakes determine how they perceive such phenomena and take action to get back to their normal life as soon as possible [5]. Despite efforts to increase the resistance of buildings, building collapse still remains one of the most common consequences of earthquakes [6]. Temporary accommodation can be very helpful in mitigating these consequences since families who have lost their homes need a private and safe place to continue their daily routine [7]. One of the most important problems after natural disasters is the provision of temporary accommodation for survivors [8].

The establishment of temporary accommodations requires evaluating different types of planning variables to select the plan with the highest effectiveness and cost-efficiency. The selected planning variables should be re-evaluated after a disaster to examine their performance and modify them if necessary [9]. Iran has often suffered from large and destructive earthquakes and has experienced several major earthquakes in the last few decades. More than 70 percent of Iran's major cities are located near seismic faults, and in some cases, active faults cross the cities [10].

This study is conducted to identify and prioritize the risks of the temporary accommodation process in possible future earthquakes in Sanandaj (the capital of Kurdistan Province in Iran). The first step in achieving this goal is to identify the challenges posed by earthquakes around the world through a comprehensive and accurate review of the literature. The identified risks and challenges are then integrated and monitored with expert opinions. In the next step, using the fuzzy Delphi method, the importance of identified risks is determined based on the characteristics of the study area.

2. LITERATURE REVIEW

2.1. Project Risk Management

Risk management consists of identifying, analyzing, and prioritizing the risks to minimize the consequences and negative impact of unfortunate events [11, 12]. It involves the use of available resources to develop solutions for reducing the risks based on their priority [13]. The risks vary from one project to another; therefore, a risk checklist should be prepared in order to have a comprehensive identification [14]. According to previous studies, historical data, experience, and judgment are the main elements in risk identification [2]. The gathered data should be examined, and the data which is more crucial in the risk management process should be dealt with in more detail. The main objective in risk identification is to highlight the most critical components of a given project during design and construction.

The prioritization of risks should be carried out carefully to sort them from the most critical with the highest probability of occurrence to the less frequent with lower impact in descending order. Using this method can save a significant portion of resources, leading to effective management of the project. In risk management, uncertainties play an important role and can make huge differences in the prioritization of risks [13]. The methods used for the identification of risks and associated uncertainties generally rely on past experience from previous projects. However, in projects with a lack of previous experience, it is important to use the opinion of experts to make a decision on prioritization of risks.

In construction projects, the risk identification procedure becomes more complex since no specific guidelines or standard procedure is available for this purpose [15]. Therefore, the experience, knowledge, and judgment of experts are usually the reference for identifying and prioritizing risks in such projects. The key to successful risk management is the risk identification step. Typically, the potential risks are identified by three different groups [16]: (i) risk analysts, (ii) experts of the project team, and (iii) brainstorming meetings. The first group identifies risks exclusively based on his/her personal experience. In the second group, each expert is interviewed to give his/her opinion about the risks relevant to his/her area of expertise. In the third group, all interested parties are asked to attend meetings to brainstorm and share their ideas.

2.2. Challenges of Temporary Accommodation

Recently, post-earthquake risk evaluation has gained the attention of the construction industry and the government since it can mitigate the adverse effects of unfortunate events on human life and the economy. Previous studies were aimed at presenting a detailed post-earthquake evaluation of risks and prioritize them based on their contribution to the total loss [6, 17-19]. Félix et al. (2015) used the predefined role of local temporary accommodation locations to assess the importance of predicting temporary accommodation [6]. This study explores the essential role of temporary accommodation location during post-disaster reconstruction programs using a literature review. It also examines common and general solutions for post-disaster temporary accommodation and outlines the strengths and weaknesses of these solutions. Finally, it provides a framework for improving and developing architectural designs to overcome problems of post-disaster temporary accommodation. They show that one of the important strategies for dealing with the challenges of temporary accommodation is to predict and equip places for this work before the earthquake. These sites can be used, depending on the main infrastructure as a default for public activities. If emergency conditions occur, they will change to the temporary accommodation quickly. These sites are then considered as a space for public use after the temporary accommodation process.

Johnson (2007) analyzed the strategic planning for post-disaster temporary accommodation. She evaluated the weaknesses and strengths of the temporary accommodation process after the earthquake in Marmara and Bloom, Turkey (1999), Armenia and Colombia (1999), Kobe Japan (1995), Greek Calmatoria (1986), Mexico City (1985), and Italy Friuli (1976). He stated that the existence of a systematic and preventive strategy is the guarantor of overcoming challenges [17].

In another research by Yüksel and Hasirci (2012), experts' opinions and those who experienced the “Kocaeli” earthquake have been collected using a 5-points Likert scale questionnaire. The study analyzed the physical and psychological expectations of earthquake victims from temporary shelters and provided suggestions for improving them, including the psychology and personal needs of victims [19].

Perrucci and Aktas (2016) draw on an extensive range of sources to assess the barriers of creating steady temporary accommodation after a natural disaster such as floods, hurricanes, tsunamis, earthquakes, etc. In their review of issues-particularly in developing countries such as Haiti, they mentioned that attention to the environmental issues and compilation of the preventive program is essential [18].

Bettemir (2016) examined the challenges of the temporary accommodation system in previous earthquakes and their costs. Two earthquakes on the 23rd of October 2011 and the 9th of November 2011 in Erciş and Van, respectively. He suggested efficient and effective management strategies about natural disasters for repairing damaged buildings and the solution for the post-earthquake housing problem. The basis of this proposal was reducing the cost, time, and environmental impacts of the event. The simulation of his proposed strategy on earthquakes shows that the existence of an appropriate strategy is essential for the immediate resolution of the housing problem [20].

After the 1995 Kobe earthquake in Japan, temporary accommodation units were ready for a maximum of one year. While many displaced people, most of whom were poor and elderly, stayed in shelters for about three years. These temporary homes were also not designed for people with disabilities. There were other problems such as being away from previous locations and necessary services such as hospitals, schools, and so on. Some analysts [21-23] have stated that separation of previous residences led to an increased percentage of suicide cases among survivors.

The number of houses damaged or destroyed after disasters is frequently large, and re-housing homeless people is one of the most important tasks of reconstruction programs. Reconstruction works often last for a long time, and during that time, it is essential to provide victims with the minimum conditions to live with dignity, privacy, and protection. Due to land leases, which must be returned to the original state, it can be said that temporary accommodations are also unstable economically and environmentally [6].

In a study investigating post-earthquake temporary complex safety management, Hui and Lv (2012) reported that the danger of fire is one of the important issues of the temporary accommodation process [24]. Creating a temporary accommodation is a necessary step in the reconstruction, and therefore, it is necessary to determine how to improve it [17].

Reviewing the literature shows that most of the previous research examines the conditions and challenges of temporary accommodation location after natural disasters occurred. However, this study tries to identify the challenges in possible future earthquakes in the study area by using past experiences and experts' opinions. This study also seeks to determine the significance of the identified risks. Therefore, the results of this study can be helpful in adopting the necessary strategies to reduce potential risks in crisis management prevention programs. In fact, the purpose of this study is to identify and evaluate the potential risks in the process of post-disaster temporary accommodation in the Kurdistan province in Iran. To achieve this, a number of risks and challenges in the process of temporary accommodation of Iran and the world were collected. The results are shown in Table 1. Then, according to the opinion of experts and their experience, a number of other probable challenges were added to this list. Finally, a total number of 94 challenges were considered.

3. RESEARCH METHODOLOGY

In terms of data collection, this research is a descriptive survey. In terms of the method also, it is a mix-mode (qualitative and quantitative). Data in this study were collected using the fuzzy Delphi method [32, 33]. According to the rules of the Delphi method, one of the most important steps is to form a panel of experts. In this panel, the opinions and judgments of experts are extracted and analyzed [34]. In consensus methods, experts are those who have knowledge about the subject of study [35]. In this study, members of the Delphi panel included 18 experienced crisis management experts from 18 departments of Kurdistan province. In addition, the practical tool for collecting data using semi-structured fuzzy Delphi questionnaires included 94 challenges regarding temporary accommodation in 11 domains, and the data analysis was carried out using the fuzzy Delphi method (Fig. 1).

Table 1.
Post-earthquake temporary accommodation challenges based on literature review.
No. Challenges References
1 Displacements' psychological problems (irritability, fear of the future, worry, humiliation, etc.) [19,21,23,25,26]
2 Outbreak of illness [18,27,28]
3 Being prolonged the period of temporary accommodation [7,17,18,20,21,22,23]
4 Lack of correct estimation of the number of people affected in a short time [17,20]
5 Incorrect evaluation and prioritization of the needs, according to the fast the need for attempts [6,20]
6 The challenge of drinking water supply [19,29]
7 Lack of equal availability to friendly human resources for residents of different sites [22]
8 The lack of prediction of prefabricated structures and conex leads to the establishment of the accommodation site being prolonged [20]
9 The reluctance of some of the victims to evacuates the temporary accommodation site due to the use of free facilities when the reconstruction is completed. [20]
10 The problem of fire [19,20,24]
11 Challenge of sewage disposal [20,22]
12 The challenge of lighting and electricity [19,20]
13 The insurance of the permanent buildings of the victims as a result of the prolongation of the reconstruction and the prolongation of the period of temporary accommodation [20]
14 The problem of victims occupation [6,25]
15 Shortage of infrastructure (water, drainage, electricity, road networks, etc.) [6]
16 Lack of formal psychiatric health services [27]
17 Medical facilities avoidance [6,21,23]
18 Disrespect to cultural and local issues [6]
19 Destruction of environmental signs [6]
20 Destruction of vegetation [6]
21 Soil degradation [6]
22 Social isolation of victims occupant in temporary accommodation away from permanent accommodation [6]
23 Occurrence of strongly floods and rains [19,30]
24 Lack of formal mental health infrastructures [21,23,27]
25 Ignoring the local context in the relief program [27]
26 The fragmentation of health care among a large number of non-governmental organizations [27]
27 Waste accumulation resulting from the Dismantlement of temporary accommodation infrastructure after the expiration of the period of residence on the rental lands [6]
28 The cold and hot challenge [19,20,25,30]
29 Change in social communication in society (social capital) [31]
30 The problem of economic activity, education, and social health [25]
31 The problem of health facilities (bathroom and toilet) [19,25,30]
32 Challenge of facilities maintenance [25,30]
33 Privacy challenge [29,30]
34 Challenging the evacuation of the temporary accommodation site by tenants and new migrants after the expiration of the temporary accommodation [17]
35 The problem of the shelter type selection [18,19,22,24,25,30]
36 Lack of sense of belonging to the location on behalf of the injured, occupant on the site [19]
37 Inadequacy of enough space in the selected shelter [22,30]
38 The issue of the accurate distribution of shelter [22]
39 People avoidance from going to camps as temporary accommodation [22]
40 Challenges of the health environment [29, 30]
41 The problem of waste disposal [29]
42 The challenge of safety management in the food supply [29]
43 The Challenge of Non-Native Immigrants [28]
44 The fruition of secondary refugee to have more comfortable facilities than victims [28]
45 The difference between women and men for availability to facilities and sense of security [28]
46 The difference in the service between temporary accommodation sites, which leads to a high population density on sites with more facilities [28]
47 The difference in services between urban and rural temporary accommodation sites will lead to an increase in demand for urban temporary accommodation sites [28]
48 The challenge of change in the diet of the injured [28]
49 The problem of coordination among service provider devices [28]
Fig. (1). Research steps of identifying the risks in the post-earthquake temporary accommodation process based on the Fuzzy Delphi technique.

The judgment of 17 experts in the area of crisis management was used to assess the validity of the questionnaire, and the Lawshe method was used to determine the content validity ratio (CVR) in each section [36]. To measure reliability, Cronbach's alpha was used in a questionnaire completed by 17 experts. Excel and SPSS software were used for data analysis.

3.1. Delphi Survey Technique

The Delphi survey technique is a communication structure whose purpose is to produce a detailed survey and discussion. Delphi studies are useful in creating regulation, standards, and predicting processes [37] and are a widespread and acceptable way for collecting information from respondents in their field of expertise. This technique was designed as a group communication process whose goal is to achieve the convergence of belief in a particular issue in the real world [38]. The Delphi technique is essentially a series of successive or periodic questionnaires combined with feedback which seeks to gain the most trusted opinion of an expert group [39].

3.2. Fuzzy Delphi Technique

A fuzzy set is a continuous group of objects with a set of continuous scores under the membership title. Such a set is characterized by a membership function (characteristic) that specifies each object with a decimal membership degree between zero and one [40]. The Delphi method is based on respondents' views. In this method, verbal expressions are used to measure the viewpoints. Verbal terms have limitations in reflecting the subjective views of respondents. For example, the term “Tall or high” for person “A” has a meaning and a certain number, and another means and another number for person “B.” In other words, although the competence and mental capabilities of experts are used to make decisions, the quantification of experts’ opinions cannot fully reflect their thinking style. The use of fuzzy sets is consistent with linguistic and sometimes vague human descriptions, and it is better to use fuzzy numbers in real-world decision making [32, 41, 42].

A triangular fuzzy digit (TFN) is a fuzzy number represented by three real numbers (f = (l, m, u)). The upper limit for the fuzzy number is f and is indicated by u, and the lower limit is indicated by l. The mean of the fuzzy number is shown with m, which has the highest possible value. The membership function of a triangular fuzzy number is as follows [32]:

(1)

The geometric image of the triangular fuzzy number (f = (l, m, u)) is displayed as follows:

The structure of fuzzy triangular numbers is very suitable for prediction by the Delphi method. In a method used to predict the time, cost, and other quantitative values, experts are asked to make their predictions based on the minimum, maximum, and most probable values. Hence, it is no longer necessary to prepare a clear and absolute value [32].

Some mathematical operations for fuzzy numbers are as follows [32]:

(2)
(3)
(4)
(5)
(6)
(7)
(8)

The Fuzzy Delphi technique algorithm contains the following steps [32]: (i) Identification and selection of appropriate fuzzy spectrum for the fuzzification of respondents' linguistic expressions, (ii) Fuzzy aggregation of values that became fuzzy (experts’ opinions should be gathered), (iii) Defuzzification of value, (iv) Selection of threshold and screening criteria. Table 2 shows the fuzzy triangular numbers for a five-point scale.

Table 2.
Triangular fuzzy numbers for the five-point Likert scale of measurement [32].
Verbal Expressions Fuzzy Numbers
Very Important (0.75, 1.00, 1.00)
Important (0.5, 0.75, 1.00)
Relatively Important (0.25, 0.5, 0.75)
Unimportant (0.00, 0.25, 0.5)
Very Unimportant (0.00, 0.00, 0.25)

4. RESULTS AND DISCUSSION

4.1. Two Steps of Fuzzy Delphi Method

Fuzzy Delphi questionnaire, along with the summary of identified challenges of previous studies (Table 1), was sent to all organizations and companies through the Kurdistan Crisis Management Office. The questionnaire included 11 areas and 94 questions, in which experts were asked to add comments to their questions in addition to answering these questions, if necessary. In the first step, the questionnaire completed by specialists and crisis management experts was sent to the crisis management directorate by 18 organizations, agencies, and companies.

In order to analyze the responses of the Fuzzy Delphi questionnaire, first, all of the answers in the 11 tables (the number of related domains) were collected in fuzzy numbers in Excel software. Then, the average total of 18 experts' answers for each question was extracted in fuzzy form. To further utilize the defuzzification method of fuzzy number, we use three different methods. The average of the defuzzification number of the three methods was determined as a defuzzification response according to Table 3 for each question.

Given that in the first step of the Fuzzy Delphi method, none of the responses were within a very small range, no questions among 94 questions were removed to continue the fuzzy Delphi process [43]. After carrying out the analysis and calculations in the first stage, again, the questionnaire, along with the results of the first step, was presented in person to the participating experts in the first stage. They were asked to compare their responses with the average of the total responses in the previous step, and offer revisions, if appropriate. The second stage questionnaire was then collected, and the results were extracted after the fuzzification and de-fuzzification, as described in Table 4.

Given that the average difference of defuzzification number in the second and the first is less than 0.1 or lower threshold of defuzzification number in the Likert five-point spectrum, another stage is not considered for the poll [43]. In other words, convergence has been achieved among experts.

4.2. Prioritization of Post-earthquake Temporary Accommodation Risks and the Area

The Prioritization in this study is based on a comparison of the defuzzification number in the fuzzy Delphi final step of each question with the defuzzification number in the Likert five-point area. The results of this prioritization are presented in Table 5, in order of priority. In addition, the total defuzzification average of all questions in each area is computed and presented in Table 6 and (Fig. 2).

The results show that, among the 94 identified risks, the challenge of cold and hot weather and the challenge of sewage disposal with a score of 0.808 are the most important. The risk of disrespectful feeling to cultural and local issues, with a score of 0.327, has the least important issue in the process of temporary accommodation after possible future earthquakes in the study area. In addition, in cross-sectoral comparison, the risks of climatic scope were the most important, with an average score of 0.698.

Table 3.
Fuzzy triangular numbers of verbal variables.
Verbal variables Triangular fuzzy number Defuzzification number based on Minkowski formula (1)
X=(l+(u-m)/4)
Defuzzification number based on formula (2)
X=(l+2m+u)/4
Defuzzification number based on formula (3)
X=(l+m+u)/3
Defuzzification number based on average of three methods
(1),(2),(3)
Very High (0.75, 1.00, 1.00) 0.75 0.9375 0.9167 0.8681
High (0.5, 0.75, 1.00) 0.5625 0.75 0.75 0.6875
Medium (0.25, 0.5, 0.75) 0.3125 0.5 0.5 0.4375
Low (0.00, 0.25, 0.5) 0.0625 0.25 0.25 0.1875
Very low (0.00, 0.00, 0.25) 0.0625 0.0625 0.0833 0.0694
Table 4.
The average of experts' opinions after the second phase of the Fuzzy Delphi survey.
Scope of Risk Risk No. Risk Name The triangular fuzzy mean of expert opinion in the second step of the Delphi method The average of experts defuzzification in first step of the Delphi method The average of experts defuzzification in second step of the Delphi method The average of experts defuzzification in first and second step of the Delphi method
l m u
Social and Cultural Scope R1 The unwillingness of people to reside on the sites of temporary accommodation outside the city 0.361 0.583 0.778 0.500 0.520 0.020
R2 Cultural differences between victims and relief experts 0.278 0.500 0.750 0.466 0.452 0.014
R3 The challenge of mutual trust between victims and reliefs 0.319 0.556 0.792 0.507 0.497 0.010
R4 The reluctance of some of the victims to evacuate the temporary accommodation site due to the use of free facilities when the reconstruction is completed. 0.292 0.528 0.750 0.475 0.465 0.010
R5 Disrespectful feeling to cultural and local issues 0.153 0.375 0.625 0.341 0.327 0.014
R6 Lack of victims participation in the site administration 0.194 0.431 0.681 0.361 0.375 0.014
R7 The challenge of rumors creation from unofficial sources 0.486 0.722 0.903 0.658 0.648 0.010
R8 Change in social communication in society (social capital) 0.292 0.528 0.778 0.459 0.459 0.014
R9 Sense of not belonging to the place from the victims residents on the site 0.403 0.639 0.833 0.568 0.568 0.000
R10 The challenges of ethnic and religious differences between the injured 0.292 0.528 0.778 0.459 0.459 0.014
R11 Problems of study continuation for the injured 0.389 0.639 0.861 0.569 0.569 0.000
R12 Non-sense of neighborhood among the injured 0.264 0.514 0.750 0.441 0.448 0.007
R13 Social isolation of victims, occupant in temporary accommodation far away from permanent accommodation 0.333 0.569 0.792 0.500 0.507 0.007
Security Scope R14 Challenge of privacy regard 0.486 0.736 0.917 0.650 0.654 0.004
R15 Entrance of non-victims and opportunists to the temporary accommodation site 0.528 0.764 0.889 0.684 0.674 0.010
R16 The challenge of non-native immigrants 0.444 0.694 0.889 0.627 0.617 0.010
R17 The difference between men and women in the sense of security 0.444 0.694 0.903 0.620 0.620 0.000
R18 Challenge of vehicles in unconventional hours and creation of noise pollution 0.347 0.583 0.806 0.530 0.520 0.010
R19 Creation of disturbance by site residents for neighbors or vice versa 0.375 0.625 0.847 0.569 0.555 0.014
R20 The conversion into these sites after the end of the temporary accommodation to crime society that operate outside the law, by new immigrants and people who do not qualify for provision of permanent accommodation. 0.375 0.611 0.903 0.574 0.568 0.006
R21 Conflict between people 0.361 0.611 0.847 0.555 0.545 0.010
Climatic Scope R22 Challenge of cold and heat 0.667 0.917 1.000 0.784 0.808 0.024
R23 Challenge of wind and storm 0.667 0.819 0.944 0.708 0.722 0.014
R24 Challenge of flood 0.514 0.764 0.903 0.664 0.671 0.007
R25 Challenge of sand storm 0.472 0.722 0.917 0.654 0.644 0.010
R26 Challenge of snow and rain 0.639 0.889 1.000 0.774 0.788 0.014
R27 Paths obstruction due to snow and rain as a result of disorderliness in the offer of winter service 0.583 0.833 0.972 0.726 0.740 0.014
R28 Inappropriate selection of shelter type based on climatic conditions 0.472 0.722 0.889 0.623 0.637 0.014
R29 Inappropriate establishment of shelter based on sunrise and sunset location and dominant wind direction 0.403 0.653 0.847 0.547 0.575 0.028
R30 Challenge of the spread of infectious diseases 0.569 0.819 0.958 0.712 0.726 0.014
R31 Challenge of availability to medication and treatment 0.514 0.764 0.958 0.672 0.686 0.014
R32 Challenge of food corruption 0.514 0.764 0.944 0.692 0.682 0.010
R33 Challenge of sewage disposal 0.667 0.917 1.000 0.797 0.808 0.010
R34 Challenge of waste disposal 0.639 0.889 1.000 0.778 0.788 0.010
R35 Division of corrupt and unstable food products among the injured 0.514 0.750 0.903 0.654 0.668 0.014
R36 Challenges for the equipment and machinery provision for shipping of patient and outpatient emergency 0.486 0.726 0.917 0.627 0.654 0.028
R37 Challenge of changing the diet of the injured 0.486 0.722 0.917 0.642 0.652 0.010
R38 Psychological problems of the injured 0.625 0.875 0.972 0.756 0.770 0.014
R39 Lack of formalized pre-provided infrastructure for the mental health of the injured 0.500 0.750 0.944 0.682 0.672 0.010
R40 Lack of formal psychiatric health services 0.514 0.764 0.944 0.692 0.682 0.010
R41 The fragmentation of health care among a large number of non-governmental organizations 0.361 0.611 0.847 0.559 0.545 0.014
Support and Logistics Scope R42 The difference between men and women to availability the facilities 0.389 0.639 0.861 0.555 0.569 0.014
R43 Easier availability for secondary refugees to facilities than the main injuries 0.264 0.500 0.750 0.459 0.445 0.014
R44 High population density at sites with more facilities 0.403 0.639 0.875 0.566 0.580 0.014
R45 Increased demand in temporary urban accommodation sites compared to temporary accommodation and rural sites 0.528 0.778 0.944 0.678 0.692 0.014
R46 Ignoring of local backgrounds in the assisting program 0.389 0.625 0.847 0.548 0.562 0.014
R47 Weakness in the distribution of shelter (tent and conex) 0.542 0.792 0.944 0.688 0.702 0.014
R48 Differences in the type of shelter offered to people during the temporary accommodation, and the creation of a sense of discrimination 0.528 0.778 0.931 0.698 0.688 0.010
R49 Lack of coordination in the distribution of humanitarian assistance 0.542 0.792 0.958 0.716 0.706 0.010
Infrastructure Scope R50 Challenge of supplying water requirements to drink and health issues 0.569 0.806 0.931 0.702 0.716 0.014
R51 Challenge of machine traffic on the paths leading to the site and their surrounding environment 0.444 0694 0.861 0.619 0.609 0.010
R52 Lack of adequate knowledge of local materials for creation of shelter and rising transportation costs 0.361 0.597 0.806 0.517 0.530 0.014
R53 Challenge of fuel supply 0.556 0.806 0.944 0.698 0.712 0.014
R54 Challenge of electricity and lighting 0.500 0.750 0.917 0.650 0.664 0.014
R55 Challenge of the inability to inventory temporary shelters for property taken out of the rubble 0.500 0.750 0.917 0.650 0.664 0.014
R56 Challenge of availability to entertainment and sports facilities according to age and gender of the injured 0.403 0.653 0.833 0.557 0.571 0.014
R57 The issue of availability to appropriate communication networks, such as the fixed telephone 0.403 0.653 0.861 0.572 0.579 0.007
R58 Challenge of riding person and pedestrian availability interference for the inside and around the site 0.375 0.625 0.819 0.533 0.547 0.014
R59 Lack of prediction of pre-event prefabricated structures and conex that prolong the launch phase of the site. 0.542 0.792 0.944 0.688 0.702 0.014
R60 Disproportionate type of shelter with accommodation duration 0.556 0.806 0.931 0.694 0.708 0.014
R61 Lack of adequate public and suitable services during temporary accommodation 0.431 0.667 0.889 0.590 0.604 0.014
R62 Lack of familiarity with the victims to maintenance of new shelters 0.389 0.625 0.861 0.566 0.566 0.000
R63 Lack of equal and optimal availability of temporary accommodation units to the welfare facilities available on the site 0.417 0.667 0.889 0.583 0.596 0.014
R64 Disproportion of the space within the temporary accommodation units with the number of households and the type of activity of the residents 0.431 0.681 0.889 0.593 0.606 0.014
R65 Non-separation of riding person and walking person availability into the temporary accommodation site 0.431 0.681 0.875 0.589 0.603 0.014
Economic Scope R66 Unemployed victims and closure of their businesses 0.625 0.875 0.972 0.742 0.770 0.028
R67 Priority of physical reconstruction on economic reconstruction 0.375 0.625 0.833 0.544 0.551 0.007
R68 The loss of young people's skills training in the creation of business during the temporary accommodation 0.347 0.597 0.806 0.509 0.523 0.014
R69 Challenge of maintaining income sources in some families during the temporary accommodation, such as livestock keeping 0.611 0.681 0.875 0.708 0.698 0.010
R70 Not having permanent insurance buildings of the victims which are not insured as a result of the prolongation of the reconstruction and the prolongation of the period of temporary accommodation 0.583 0.833 0.987 0.734 0.744 0.010
Environmental Scope R71 Destruction of environmental signs 0.444 0.681 0.903 0.604 0.618 0.014
R72 Destruction of vegetation 0.347 0.583 0.819 0.510 0.524 0.014
R73 Soil degradation 0.278 0.500 0.722 0.431 0.444 0.014
R74 Damaging forests and pastures 0.306 0.556 0.792 0.475 0.489 0.014
R75 Accumulation of waste and materials due to the destruction of the site after the end of temporary accommodation 0.403 0.639 0.847 0.582 0.572 0.010
Scope of Ownership and Legal Issues R76 Installation of prefabricated units on private lands and in the vicinity of damaged homes. Creation of reconstruction problems and elimination debris 0.403 0.653 0.875 0.569 0.583 0.014
R77 Putting the conex on the land belonging to other people 0.403 0.653 0.875 0.544 0.551 0.007
R78 Arbitrary use of the victims' lands and private estates around the site as a warehouse, parking, and ... 0.375 0.625 0.833 0.630 0.644 0.014
Events Scope R79 Fire on the site 0.372 0.722 0.917 0.562 0.568 0.007
R80 electrocution 0.403 0.639 0.833 0.510 0.524 0.014
R81 Vehicle crash with people 0.361 0.583 0.792 0.362 0.348 0.014
R82 Damages resulting from animals and insects hart to people (snake, scorpion, etc.) 0.181 0.389 0.639 0.578 0.592 0.014
Management Scope R83 Lack of centralized management based on existing potential in the region and coordination between service providers 0.431 0.667 0.847 0.617 0.606 0.010
R84 Inappropriate placement of the temporary accommodation site and non-attention to the relevant criteria (Such as availability to services, avoidance of faults and streams, gas lines, and ...) 0.431 0.681 0.889 0.706 0.716 0.010
R85 The desire of some organizations to prioritization of their organization instead of integrated crisis management brief and agreements 0.556 0.806 0.958 0.599 0.589 0.010
R86 Lack of correctly estimate about the number of people who go to other cities after of earthquake. 0.417 0.667 0.861 0.586 0.576 0.010
R87 Evaluation and prioritization of the needs 0.403 0.639 0.861 0.606 0.596 0.010
R88 Lack of coordinating reconstruction of permanent buildings in pre-specified temporary accommodation 0.417 0.667 0.889 0.638 0.628 0.010
R89 Non conformity of the procedure unity and using different methods 0.444 0.694 0.931 0.603 0.693 0.010
R90 Lack of assessment of the post-earthquake local workforce, for the temporary accommodation period and permanent accommodation reconstruction 0.417 0.667 0.875 0.561 0.551 0.010
R91 Lack of same procedure in the assessment of earthquake effects 0.375 0.625 0.833 0.568 0.582 0.014
R92 The lack of a pre-codification evaluation plan for responsibility and accountability 0.417 0.653 0.847 0.586 0.590 0.004
R93 Lack of predicting the number of victims on preventive planning before the earthquake 0.431 0.653 0.847 0.613 0.627 0.014
R94 Challenge of coordination between service providers during temporary accommodation 0.458 0.708 0.889 0.640 0.630 0.010
Table 5.
Prioritized of risks and their relevance in the post-earthquake temporary accommodation process based on the average of three methods of defuzzification in the Fuzzy Delphi technique.
Priority Risk No. Risk rating Risk level Priority Risk No. Risk rating Risk level Priority Risk No. Risk rating Risk level
R22 0.808 Very High R7 0.648 High R20 0.568 High
R33 0.808 Very High R25 0.644 High R79 0.568 High
R26 0.788 Very High R78 0.644 High R62 0.566 High
R34 0.788 Very High R28 0.637 High R67 0.562 High
R38 0.770 Very High R94 0.630 High R46 0.555 High
R66 0.770 Very High R88 0.628 High R19 0.551 High
R70 0.744 High R93 0.627 High R77 0.551 High
R27 0.740 High R17 0.620 High R90 0.551 High
R30 0.726 High R71 0.618 High R58 0.547 High
R23 0.722 High R16 0.617 High R21 0.545 High
R50 0.716 High R51 0.609 High R41 0.545 High
R84 0.716 High R64 0.606 High R52 0.530 High
R53 0.712 High R83 0.606 High R72 0.524 High
R60 0.708 High R61 0.604 High R80 0.524 High
R49 0.706 High R65 0.603 High R68 0.523 High
R47 0.702 High R63 0.596 High R1 0.520 High
R59 0.702 High R87 0.596 High R18 0.520 High
R69 0.698 High R89 0.593 High R13 0.507 High
R45 0.692 High R82 0.592 High R3 0.497 High
R48 0.688 High R92 0.590 High R74 0.489 High
R31 0.686 High R85 0.589 High R8 0.473 High
R32 0.682 High R76 0.583 High R10 0.473 High
R40 0.682 High R91 0.582 High R4 0.465 High
R15 0.674 High R44 0.580 High R2 0.452 High
R39 0.672 High R57 0.579 High R12 0.448 High
R24 0.671 High R86 0.576 High R43 0.445 High
R35 0.668 High R29 0.575 High R73 0.444 High
R54 0.664 High R75 0.572 High R6 0.375 Medium
R55 0.664 High R56 0.571 High R81 0.348 Medium
R14 0.654 High R11 0.569 High
R36 0.654 High R42 0.569 High R5 0.327 Medium
R37 0.652 High R9 0.568 High
Table 6.
Prioritization of different risk areas in the post-earthquake temporary accommodation process based on the defuzzification average of experts' opinions.
Priority No. Scope Name Defuzzification average of experts' opinions
1 Climatic Scope 0.698
2 Healthcare Scope 0.694
3 Economics Scope 0.657
4 Infrastructure Scope 0.624
5 Procurement and Support Scope 0.618
6 Management Scope 0.607
7 Security Scope 0.594
8 Scope of Ownership and Legal Issues 0.593
9 Environmental Scope 0.530
10 Scope of Events 0.508
11 Social and cultural Scope 0.486
Fig. (2). Defuzzification average diagram opinion of experts for various risk areas in the post-earthquake temporary accommodation process.

CONCLUSION

This research was carried out to answer the two following questions: (i) What are the risks in the post-earthquake temporary accommodation process? and (ii) What is the priority of the risks in the post-earthquake temporary accommodation process? To this end, first, the theoretical basis of the temporary accommodation process after natural and unnatural disasters was studied. Then, challenges of the temporary accommodation process were collected through previous reports and research on temporary accommodation, and experienced experts’ opinions gathered through interviews. Finally, 94 challenges were collected. The Delphi method was used to evaluate the identified risks. The consensus among experts to determine the significance of each risk was reached after two rounds of fuzzy Delphi. The results of the Delphi method were analyzed using fuzzy triangular numbers. Finally, the risks were ranked according to their importance. The study results show that all 94 identified risks are of medium and high importance in the post-earthquake temporary accommodation process. In this study, the risks were identified and evaluated based on the characteristics of the study area. Therefore, it is suggested that areas with different characteristics should be studied for future studies. Identifying the risks of the temporary post-earthquake resettlement process can help develop a disaster prevention plan. It can also help promote various aspects of sustainable development, including social, environmental, and economic aspects.

CONSENT FOR PUBLICATION

Not applicable.

AVAILABILITY OF DATA AND MATERIALS

The data used to support the findings of this study are included in the article.

FUNDING

None.

CONFLICT OF INTEREST

The authors declare no conflict of interest, financial or otherwise.

ACKNOWLEDGEMENTS

Declared none.

REFERENCES

1
Winarno S, Griffith A, Stephenson P. Reducing earthquake risk to non-engineered buildings: A study of design and construction practices in Indonesia. Int J Const Manag 2010; 10(1): 75-86.
2
Sarvari H, Rakhshanifar M, Tamošaitienė J, Chan DWM, Beer M. A risk based approach to evaluating the impacts of Zayanderood drought on sustainable development indicators of Riverside Urban in Isfahan-Iran. Sustainability - Special Issue on Sustainability and Risks in Construction Management 2019; 11(23)
3
Adamy A, Abu Bakar AH. Developing a building-performance evaluation framework for post-disaster reconstruction: the case of hospital buildings in Aceh, Indonesia. Int J Const Manag 2021; 21(1): 56-77.
4
Félix D, Branco JM, Feio A. Temporary housing after disasters: A state of the art survey. Habitat Int 2013; 40: 136-41.
5
Becker JS, Paton D, Johnston DM, Ronan KR, McClure J. The role of prior experience in informing and motivating earthquake preparedness. Int J Disaster Risk Reduct 2017; 22: 179-93.
6
Félix D, Monteiro D, Branco JM, Bologna R, Feio A. The role of temporary accommodation buildings for post-disaster housing reconstruction. J Housing Built Environ 2015; 30(4): 683-99.
7
Johnson C. Impacts of prefabricated temporary housing after disasters: 1999 earthquakes in Turkey. Habitat Int 2007; 31: 36-52.
8
Dabiri M, Oghabi M, Sarvari H, Sabeti M, Kashefi H. A combination risk-based approach to post-earthquake temporary accommodation site selection: A case study in Iran. Iranian Journal of Fuzzy Systems 2020; 17(6): 54-74.
9
Johnson C. What’s the Big Deal about Temporary Housing? Planning Considerations for Temporary Accommodation after Disasters: Example of the 1999 Turkish Earthquakes 2000.
10
Izadkhah YO, Amini Hosseini K. An evaluation of disaster preparedness in four major earthquakes in Iran. Journal of Seismology and Earthquake Engineering 2010; 12(1-2): 61-75.
11
APM. Project Risk Analysis and Management—Mini Guide Association for Project Management 2018. Available online: https://www.apm.org.uk/media/10466/pram_web.pdf
12
PMI. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) 6th Edition. 2017.
13
Sarvari H, Valipour A, Yahya N, Noor NM, Beer M, Banaitiene N. Approaches to risk identification in public–private partnership projects: Malaysian private partners’ overview. Adm Sci 2019; 9(1): 17.
14
Valipour A, Sarvari H, Tamošaitiene J. Risk assessment in PPP projects by applying different MCDM methods and comparative results analysis. Adm Sci 2018; 8(4): 80.
15
Rafaat R, Osman H, Georgy M, Elsaid M. Preferred risk allocation in Egypt’s water sector PPPs. International Journal of Construction Management 2020; 20(6): 585-97.
16
Chapman RJ. The effectiveness of working group risk identification and assessment techniques. Int J Proj Manag 1998; 16(6): 333-43.
17
Johnson C. Strategic planning for post-disaster temporary housing. Disasters 2007; 31(4): 435-58.
18
Perrucci DV, Vazquez BA, Aktas CB. Sustainable Temporary Housing: Global Trends and Outlook, International Conference on Sustainable Design, Engineering and Construction. Procedia Eng 2016; 145: 327-32.
19
Yüksel B, Hasircl D. An analysis of physical and psychological expectations of earthquake victims from temporary shelters: A design proposal. METU Journal of the Faculty of Architecture 2012; 29(1): 225-41.
20
Bettemir ÖH. Recommendations on the solution of accommodation problem and recovery after destructive earthquakes. Int J Emerg Manag 2016; 12(2): 168-84.
21
Comerio M. Disaster hits home: New policy for urban housing recovery 1998.
22
Omidvar B, Binesh N. Reconstruction experience of Lorestan 2006 earthquake: Elimination of transitional shelter. Disaster Adv 2012; 5(1): 37-43.
23
Tomioka T. Housing reconstruction measures from the great Hanshin-Awaji earthquake Proceeding of the 5th United States/Japan Workshop on Earthquake Hazard Reduction Pasadena. 1997.1997.
24
Hui LV. “Study on Safety Management of the Temporary Community after the Earthquake, International Symposium on Safety Science and Engineering in China”, 2012 (ISSSE-2012). Procedia Eng 2012; 43: 214-20.
25
Tierney K, Tobin T, Khazai B, Krimgold F, Parsizadeh F. Reconnaissance report on Bam Earthquake social and public policy issues.Journal of Seismology and Earthquake Engineering - Special Issue on Bam Earthquake 2004; 209-15.
26
C., Cervello’n, P., Pe’rez-Salesc, P., Vidales, D., and Gaborit, M., “Positive emotions in earthquake survivors in El Salvador (2001). Anxiety Disorders 2005; 19(3): 313-28.
27
Raviola G, Severe J, Therosme T, Oswald C, Belkin G, Eustache E. The 2010 Haiti earthquake response. Psychiatr Clin North Am 2013; 36(3): 431-50.
28
Shahab Uddin Md. Surges of Earthquake displaced Population and Dynamics of Emergency Shelter Facilities: Learning from Nepal Earthquake 2015 Proceedings of the International Conference on Disaster Management: From Polar Region to the Local Communities Social and Environmental Development 2016.
29
Cordero-Reyes AM, Palacios I, Ramia D, et al. Natural disaster management: experience of an academic institution after a 7.8 magnitude earthquake in Ecuador. Public Health 2017; 144: 134-41.
30
Asefi M, Farrokhi Sh. Proposing a model for the design of post-disaster temporary housing based on the needs of the injured with post-implementation evaluation approach (Case study: Earthquake-stricken villages in Heris of East Azerbaijan). Journal of Research and Rural Planning 2018; 7(1): 81-101.
31
Nomura S, Parsons AJ, Hirabayash M, Kinoshita R, Liao Y, Hodgson S. Social determinants of mid- to long-term disaster impacts on health: A systematic review. Int J Disaster Risk Reduct 2016; 16: 53-67.
32
Habibi A, Jahantigh FF, Sarafrazi A. Fuzzy Delphi technique for forecasting and screening items. Asian Journal of Research in Business Economics and Management 2015; 5(2): 130-43.
33
Khoshfetrat R, Sarvari H, Chan DWM, Rakhshanifar M. Critical risk factors for implementing building information modelling (BIM): a Delphi-based survey.International Journal of Construction Management 2021; 1-10.
34
Yousuf MI. The Delphi technique. Essays in Education 2007; 20(1): 8.
35
McMillan SS, King M, Tully MP. How to use the nominal group and Delphi techniques. Int J Clin Pharm 2016; 38(3): 655-62.
36
Lawshe CH. A quantitative approach to content validity. Person Psychol 1975; 28(4): 563-75.
37
Green RA. The Delphi Technique in Educational Research. SAGE Open 2014; 4(2): 1-8.
38
Olawumi TO, Chan DWM. Critical success factors for implementing building information modelling and sustainability practices in construction projects: A Delphi survey. Sustain Dev 2019; 27(4): 587-602.
39
Chan DWM, Chan JHL. Developing a Performance Measurement Index (PMI) for target cost contracts in construction: A Delphi study. Const Law J 2012; 28(8): 590-613.
40
Zadeh LA. Fuzzy sets. Inf Control 1965; 8: 338-53.
41
Sarvari H, Chan DWM, Banaitiene N, Noor NM, Beer M. “Barriers to development of private sector investment in water and sewage industry”, Built Environment Project and Asset Management - Special Issue on “Public-Private Partnerships - Theory vs Practice. Charting New Trajectories 2021; 11(1): 52-70.
42
Tamošaitienė J, Sarvari H, Chan DWM, Cristofaro M. Assessing the barriers and risks to private sector participation in infrastructure construction projects in developing countries of Middle East 2021.
43
Cheng CH, Lin Y. Evaluating the best main battle tank using fuzzy decision theory with linguistic criteria evaluation. Eur J Oper Res 2002; 142(1): 174-86.