RESEARCH ARTICLE
Study on Bearing Capacity of Prestressed Pipe Pile Foundation Under Horizontal Load
Jin Xu1, 2, *, Lin Ma1
Article Information
Identifiers and Pagination:
Year: 2017Volume: 11
First Page: 301
Last Page: 312
Publisher ID: TOBCTJ-11-301
DOI: 10.2174/1874836801711010301
Article History:
Received Date: 12/06/2017Revision Received Date: 24/10/2017
Acceptance Date: 03/11/2017
Electronic publication date: 24/11/2017
Collection year: 2017
open-access license: This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International Public License (CC-BY 4.0), a copy of which is available at: https://creativecommons.org/licenses/by/4.0/legalcode. This license permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.
Abstract
Background and Objective:
Prestressed high strength concrete pipe pile (PHC) shows brittle fracture when subjected to more than its own bearing capacity. Therefore, the non-prestressed steel bar is added to the PHC pipe pile, that is, the mixed reinforced pipe pile (PRC). The mechanical behavior of PRC group piles and PHC group piles under horizontal force is studied, and the bending moment diagram and displacement diagram of the pile body are compared so as to find the weak parts.
Material and Method:
In this paper, Φ600 pipe piles are chosen, and the PRC pipe piles are made of non prestressed steel bars of the same number as the prestressing steel bars, and the two steel bars are spaced apart. Referring to a specific project of Binhai New Area, the geological parameters are used, and the force analysis of group piles under horizontal force is carried out by using the ANSYS software.
Results:
ANSYS simulation results show that, under the horizontal loading, when the number of piles in group piles is different, the locations of maximum bending moments are different. Increasing the number of the PRC pipe pile with non prestressed reinforcement can effectively reduce the maximum bending moment of the pile body.
Conclusion:
Under horizontal load, with the increase of pile number and the pile cap aggrandizement, the position of maximum moment of pile body is shifted from 5-8 times diameter of pile to the top of pile. When the pile number reaches a certain amount, the maximum bending moment will appear at the joint between the pile cap and the pile body. At the same time, increasing the non prestressed steel bar does not influence the bending moment, and the reinforcement of the pile cap and the pile top should be strengthened.