Reviewing Construction Schedule Float Management



Jyh-Bin Yang*
Graduate Institute of Construction Engineering and Management, National Central University, Taiwan


© Jyh-Bin Yang; Licensee Bentham Open.

open-access license: This is an open access article licensed under the terms of the Creative Commons Attribution-Non-Commercial 4.0 International Public License (CC BY-NC 4.0) (https://creativecommons.org/licenses/by-nc/4.0/legalcode), which permits unrestricted, non-commercial use, distribution and reproduction in any medium, provided the work is properly cited.

* Address correspondence to this author at the No. 300, Zhongda Rd., Zhongli District, Taoyuan City 32001, Taiwan (R.O.C.); Tel: +886 3 4227151 ext. 34040; Fax: +886 3 4257092; E-mail: jyhbin@ncu.edu.tw


Abstract

As the complexity in construction projects increased, simply managing the obtained float values and critical path(s) by the CPM method usually results in more difficult schedule control and, consequently, in incorrect decision making due to non-realistic float values. This study thoroughly reviewed various float types in the literature and professional project management systems, and discussed five managerial essentials and three proactive strategies on mitigating challenging float-related problems based on the perspective of managing schedules by controlling floats. With some comments and suggestions, the outcomes of this study not only improve the knowledge level on schedule management but also provide a better understanding of float management to improve the quality of schedule management.

Keywords: Critical path method, Float management, Float, Project management, Review research, Schedule management.